Dresden Island Valve Work
The contractor at Dresden Island Lock is starting valve recess work today, they have taken the chamber to install the lower bulk heads. Estimated time they are in the chamber is two hours. Once both sets of bulk heads are installed on the I-wall side we will be locking with only land wall valves. So lockage times are going to be increased. Once they are finished with the I-wall side they will then immediately start on land wall. Total estimated time for all the valves to be completed is roughly 14 to 15 days.